Expansion of De Onlanden balancing lake to start in September

The Noorderzijlvest Water Authority can start expanding the balancing lake De Onlanden in September 2025. On August 14, the Provincial Executive of Drenthe approved the project decision for the construction of balancing lake additional balancing lake De Onlanden. The additional balancing lake the storage capacity of De Onlanden within the existing quays from 7.5 to 12.7 million cubic meters. This expansion will make it possible to temporarily store more water in extreme weather conditions before it is discharged into the sea. The additional balancing lake is expected to be partially operational balancing lake 2025/beginning of 2026 and fully completed in 2027.

Work activities

The Hooiweg variant was chosen for the implementation of the work. With the project decision, phase one of this variant, the enlargement of the balancing lake, can be carried out. Two new weirs will be weirs the Hooiweg. When the extra balancing lake is used, these weirs balancing lake weirs to retain water. The water authority will also modify water authority Doolhof weir in the Peizerdiep and raise the quays in the water storage area. In addition, the water authority will increase water authority pumping capacity of pumping station , raise the access roads of TenneT and Gasunie, and take protective measures for homes on Roderwolderweg and Moleneind. Noorderzijlvest will also modify the capacity of pumping station . Although this pumping station is located pumping station the project area, it does discharge into De Onlanden. The water authority is therefore including water authority adjustments.

Additional capacity to collect water

The additional balancing lake another 5.2 million cubic meters of water. During heavy rainfall, the water level can rise to a maximum of +18 cm NAP (previously -0.20 NAP). This means that in extreme situations, more water can be temporarily stored (for a number of days) before it is discharged into the sea. 

De Onlanden water storage facility: The Eelderdiep in De Onlanden. The Eelderdiep in De Onlanden. The additional balancing lake necessary to continue to provide sufficient safety to residents around De Onlanden and in the wider region . The additional balancing lake only balancing lake used temporarily in extreme weather conditions.
The Eelderdiep in De Onlanden. The additional balancing lake necessary to continue to provide sufficient safety to residents around De Onlanden and in the wider region . The additional balancing lake only balancing lake used temporarily in extreme weather conditions.

Nature

The expansion will take the natural environment in De Onlanden into account as much as possible.  Refuge mounds will be created for animals during high water levels, the water authority fill in ditches to retain seepage water for longer, soil will be stripped along ditches, a slenk will be constructed, and the water level will be raised in parts of the area. These measures, which have been developed in collaboration with nature organizations and site managers, will strengthen the marshland nature and make the ecosystem more robust. The area between the Hooiweg and the Leekstermeer will remain outside the additional balancing lake, as it is an important breeding and living area for birds. Some of the nature measures will be implemented in phase one, at the same time as the expansion of the balancing lake. The remaining measures will follow in phase two of the project. 

From design to project decision

The draft project decision for the additional balancing lake for inspection from December 19, 2024, to January 30, 2025. A total of eighty opinions were received. These opinions were carefully considered by the province when adopting the project decision. Based on the opinions and discussions with local residents, additional measures and customized solutions were included in the final draft. The project decision will take effect four weeks after publication. Appeals against the project decision can be lodged with the Administrative Law Division of the Council of State for a period of six weeks (from August 21 to October 1, 2025). 

Limiting flooding

Accelerated climate change is increasing the risk of flooding in the northern Netherlands. As part of the Dry Feet 2050 project, the northern provinces and water boards have investigated what measures are needed to limit flooding until 2050. Denk additional balancing lake, improved control of pumping stations, raising quays, and reinforcing dykes. The optimization of De Onlanden, which has been designated as a water storage area since 2012, is an important part of this project.