Planning and information - Runsloot and Stroetenloop

In 2018, the General Board gave the green light for the exploration of the Runsloot-Stroetenloop project.During this phase, it became apparent that not all WFD targets were achievable and that not all opportunities for the stream system had been fully identified. New insights led to a reassessment of the plan in 2025. In October 2025, the General Board approved this reassessment.

Plan development

A project team has now been formed to work on this task. The exploratory phase has been completed in collaboration with engineering firm Sweco. We are now moving on to the plan development phase, in which the plans will be finalized and elaborated. In doing so, we will take into account the environment, natural values, and technical feasibility. A pilot project is being carried out in the Runsloot. The results of this project may be useful for both the Runsloot and the Stroetenloop. At the beginning of 2026, we will organize an information meeting in the area about this pilot project.

The schedule below is an estimate.

Planning Date
Action plan for the Runsloot pilot project      November 2025
Monitoring plan for the Runsloot pilot project       November 2025
Establishing pilot project areas     November 2025
Applications for permits for pilot project areas       December 2025
Newsletter Runsloot-Stroetenloop   December 2025
Information meeting for the start of the Runsloot pilot projectEarly 2026
Integrated Action Plan for Runsloot and Stroetenloop First quarter of 2026
Start of Runsloot pilot projectFirst quarter of 2026
Preliminary Design (PD) for Runsloot and Stroetenloop completedFirst quarter of 2026
Information meeting VO Runsloot and StroetenloopFirst quarter of 2026
Final design (FD) for Runsloot and Stroetenloop completed   Second quarter of 2026
Tendering and awarding of contracts    Third quarter of 2026
Memo (results from the Runsloot pilot project with recommendations for application in Runsloot and Stroetenloop)First quarter of 2027
Work complete     First quarter of 2027

Contact

Project Manager: Theo Sikkema
Environmental Manager Eddi Ottens
Contact details: runsloot-stroetenloop@noorderzijlvest.nl
 

For questions and information, please contact environmental manager Eddi Ottens at +31 (0) 6-51403752.