The procurement schedule sets out the scheduled procurement procedures for the year 2026: European tenders and selected tender procedures.

Abbreviations used in the tendering procedure 

Tendering procedure

Abbreviations

European tenderEA
National public tenderNO
Selected tender procedureMV
Procurement schedule 2026

Name of tender

Description of order

Expected Publication Date

Procedure

Communication servicesFramework Agreement for Communication ServicesFirst quarter of 2026EA
Waste servicesThe collection, transportation, and processing of waste.Second quarter of 2026EA
WorkwearPurchasing workwear and personal protective equipmentSecond quarter of 2026EA
Accounting servicesFramework agreement for accounting servicesSecond quarter of 2026EA
Construction and Assembly Insurance (CAR)Taking out new construction and assembly insuranceSecond quarter of 2026EA
ICT HardwareFramework agreement for the supply of ICT hardwareFourth quarter of 2026EA
Vehicle fleet leasingConcluding contracts for leasing the vehicle fleet EA
Supply of nitrate sensorsSupplying nitrate sensors for the lake Lauwersmeer monitoring networkSecond quarter of 2026MV
Purchase of two hydraulic cranes, north/south teamSupplying two hydraulic excavators and attachmentsFirst quarter of 2026EA
Purchase of 1 broad-track crane Supply agreement for 1 broad-track craneSecond quarter of 2026EA
Service and Maintenance for screenings-removoval systems Framework agreement for service and maintenance of screenings removal systemsSecond quarter of 2026MV
Brons engines maintenanceMaintaining Brons engines in useThird quarter of 2026EA
Warehouse stocksSupplying technical, electrical, and hydraulic productsFirst quarter of 2026EA
Replacement of hardware and terminals on weighbridgeReplacing hardware and terminals Third quarter of 2026MV
Mechanical work AWK + WSWVFramework Agreement Mechanical Work Wastewater Chain + Water Systems and SafetyFourth quarter of 2026EA
Repair of biogas tankReplacement of inner and outer balloon biogas holderSecond quarter of 2026MV
Testing, inspection, and repair of work equipmentFramework agreement for the testing, inspection, and repair of work equipmentFirst quarter of 2026EA
Purchase of flow metersFramework agreement for the purchase and maintenance of flow metersThird quarter of 2026EA
Rental Emergency PumpsAgreement for the rental of temporary pumps for scheduled maintenanceSecond quarter of 2026EA
ElectricityFramework agreement for electricityFourth quarter of 2026EA
Replacement of chemical dosing systems at Garmerwolde wastewater treatment plantReplacement of chemical dosing systemsSecond quarter of 2026MV
Heaters Garmerwolde wastewater treatment plantPurchase of 4 heatersFirst quarter of 2026MV
Hiring temporary pumping installation for Leek wastewater treatment plantSupplying and installing a temporary pump installation for the Leek wastewater treatment plantSecond quarter of 2026EA
Purchase/installation of temporary office unitsSupplying and installing temporary office units at 4 sitessecond quarter of 2026MV
Fire, burglar, and emergency response system notificationPurchase of emergency response, fire, and burglar alarm systems for the Garmerwolde wastewater treatment plantSecond quarter of 2026MV
Restoration of the Aduarderzijl lockkeeper's houseRestoring the roof and facade of the lockkeeper's houseSecond quarter of 2026MV
Clevering locksReplacement of Clevering locks control systemFourth quarter of 2026EA
Restoration of Veenhuizen Locks Restoring the lock complex First quarter of 2026MV
Contaminated dredging work BoterdiepDredging and removal of contaminated soil Fourth quarter of 2026MV
WFD nature-friendly banksImplementation of WFD measures; nature-friendly banksSecond quarter of 2026MV
Measures Spijksterpompen and Fivelingo Water Level Regulation PlanImplementation of Water Level Regulation Plan measuresSecond quarter of 2026NO
Sandebuur pumping station (Onlanden)Renovation of the current pumping stationFirst quarter of 2026 
Spijksterpompen structuresImplementation of Spijksterpompen Water Level Regulation PlanThird quarter of 2026MV
Drilling of pressure pipe Roden-BoterdijkReplacing existing inverted syphons with drilled pressure pipes Roden-BoterdijkSecond quarter of 2026MV
Plan Development and Implementation 8 Fish PassagesResolving 8 fish migration bottlenecksFirst quarter of 2026EA
Reinforcement of HoornsedijkReinforcing the Hoornsedijk flood embankmentSecond quarter of 2026MV