Schedule and access improvements for Hoornsedijk and Meerweg

The work on Hoornsedijk and Meerweg is being planned carefully and coordinated with other projects in the area.

Obstructions

The water authority is conducting work on the west side of dyke. This work will not result in closures of the dyke.

Obstruction due to work on beaver mesh

Work on the beaver mesh will take place from 31 August to 9 September. 

  • For this reason, a section of the dyke will be closed on weekdays from 7:00 to 16:00.
  • The closure applies roughly to the section between house numbers 17 and 20. 
  • The dyke will be accessible again after 16:00. 
  • The dyke is accessible on weekends.
  • Smart Map Groningen Bereikbaar (Hoornsedijk Haren Gn Redevelopment / Maintenance of Other)

Next: Road closure for asphalt replacement by Groningen Council

Next, the council will replace the asphalt on this section of the dyke. Road closures will also be in effect for this project. The council will provide further information ar “Groningen Bereikbaar”: Smart Map Groningen Bereikbaar
 

Coordination with other projects

The work on Hoornsedijk and Meerweg is being planned carefully and coordinated with other projects in the area.

  • August 2026: Preparation and start of work on dyke stabilisation
  • Autumn 2026: First phase of beaver mesh installation, combined with roadwork
  • December 2026: Preparation and start of work to install beaver mesh on Meerweg
  • 2027: Second and, if necessary, third phase of the beaver mesh at Hoornsedijk

Here's how we minimise disruption

By working together with the Groningen Council and the provincial executive, we ensure that residents experience as little disruption as possible and that work is carried out simultaneously whenever possible.