Restoration of Zuidema's Klap drawbridge

The water board has restored the Zuidema's Klap drawbridge near Niekerk (Leens). The restoration has now been completed. The bridge has been open to road traffic again since July 23, 2021.

Implementation phase

During the work, the bridge was closed to traffic. It was dismantled and transported to a workshop where it was repaired. After repair, the bridge was put back in place. Local traffic on Kanaalstraat and Aikemapad near Niekerk was diverted during the work period by means of signage.

History

The monumental drawbridge Zuidema's Klap is located at the junction of Kanaalstraat and Wester Aikemapad near Niekerk (Leens). The bridge spans the Hunsingo Canal. It was built in 1879 and is a national monument. There is an axle load restriction due to defects identified in a structural survey. The Noorderzijlvest Water Authority has made funds available to prepare for the restoration of the bridge in 2018 and then to restore it.

Restored bridge Zuidemas Klap

Planning: Restoration of Zuidema's Klap drawbridge

  • Preparation for summer 2020
  • Restoration to begin at the end of September 2020
  • Completion July 23, 2021